Estimated Timeline of Completion

3 years ago

  • Design process begins immediately and construction documents issued by the end of 2021

  • Construction of Secondary Facility begins January 2022 (expected to take 12 months to construct)

  • Once the secondary facility is occupied, renovations and remodeling of elementary would begin

  • Once the remodeled elementary is occupied, demolition of existing elementary wing would begin 

  • We are expecting this process to take 18-24 months to complete once construction begins